Nessel needs Line 5 evicted from tribal land, Republicans decry ‘pointless delays’ for tunnel

The identical day that Michigan Lawyer Basic Dana Nessel filed a authorized temporary searching for to eject the Line 5 pipeline from tribal land in Wisconsin, the Michigan Senate Republican caucus on Wednesday held a press convention to criticize “pointless delays” in approving permits for Enbridge’s Nice Lakes Tunnel Venture encasing Line 5 because it crosses the Straits of Mackinac.
All 18 of Michigan’s GOP senators gathered in Lansing to comply with up on a letter the caucus despatched to Gov. Gretchen Whitmer and Lt. Gen. Scott A. Spellmon, chief of engineers and commanding basic of the U.S. Military Corps of Engineers (USACE), urging that the allowing course of for the undertaking be expedited. The letter famous that building on the undertaking was initially scheduled to start in 2021, with the tunnel anticipated to be operational by 2024.
“We have to cease on this state the all-out assault on the power trade that we’re endeavor proper now,” mentioned state Sen. John Damoose (R-Harbor Springs), who represents the Straits space. “There’s a push to eliminate your complete oil and fuel trade, which is totally irresponsible. And make no mistake, the assault on Line 5 is strictly that, a push to eliminate the oil and fuel trade. The actual fact is, we could possibly be midway achieved with this tunnel proper now if all people would cease dragging their toes and do their jobs. 1000’s of nice Michigan laborers may at this very second be working within the Straits of Mackinac to construct this tunnel. In truth, this tunnel was one thing all of us ought to have been happy with.”
Line 5 is owned and operated by Canadian power firm Enbridge, which utilized for a allow with USACE in April 2020 pursuant to the Rivers and Harbors Act of 1899 and the Clear Water Act. Federal approval is critical for the undertaking because it entails discharging dredged or fill supplies into waters of america, in addition to the development of buildings and/or work that will have an effect on navigable waters.
In response to the GOP criticism, USACE spokesperson Emily Schaefer informed the Michigan Advance that the method has been a consultative one with all involved.
“The U.S. Military Corps of Engineers (USACE) is following the procedures and steerage for getting ready a Nationwide Environmental Coverage Act Environmental Impression Assertion (EIS),” she mentioned. “An EIS is warranted based mostly on the Enbridge Line 5 Pipeline Tunnel undertaking’s potential to have vital impacts on the standard of the human setting. USACE up to date the schedule in March 2023 following evaluation and consideration of enter from the EIS public scoping periods. USACE consulted with Enbridge concerning the EIS schedule, and the schedule represents a practical timeline for improvement of an EIS, based mostly on an understanding of the research and session essential to help the EIS.”
The EIS beforehand had a deliberate publishing timeframe of late 2023, however was pushed again to spring 2025, doubtless that means the earliest building may start is 2026.
Enbridge additionally requires allowing approval from the Michigan Public Service Fee (MPSC), which issued a press release concerning the course of.
“Enbridge’s software is a fancy matter, and the Fee has taken various steps because the case was filed, together with addressing the scope of the problems to be thought-about in April 2021 and reopening the document in July 2022 to assemble extra proof on engineering and security issues vital to the proposed undertaking. A case this vital deserves strong deliberation, and the Fee will concern its order in the end,” mentioned the company.
The third entity wanted to offer permits for the tunnel undertaking is the Division of Surroundings, Nice Lakes and Vitality (EGLE), which, thus far, is the one one to truly grant them. Additionally it is the one state-run company concerned within the course of. The MPSC is an impartial regulatory physique whereas USACE is a federal company.

Whitmer opposes the Line 5 pipeline and ordered Enbridge to decommission Line 5 by spring 2021. The corporate has refused and the matter has been tied up in court docket.
Zack Pohl, Whitmer’s deputy chief of employees, responded to the GOP letter.
“These pipelines, which have been struck by anchors and different objects a number of occasions previously 5 years, are a ticking time bomb that put Michigan’s water and 350,000 Michigan jobs in danger,” he mentioned. “The truth that Senate Republicans held a press convention advocating for a Canadian oil firm that was answerable for the most important oil spill in state historical past – the identical day a BP fuel pipeline ruptured and spilled hundreds of gallons of gasoline in Department County – exhibits simply how out of contact they’re with regards to defending Michigan water and Michigan jobs. Whereas Senate Republicans waste time on foolish partisan video games, the governor will stay centered on defending the Nice Lakes and Michigan jobs.”
Sean McBrearty is the marketing campaign coordinator for Oil & Water Don’t Combine, an environmental advocacy group that steadfastly opposes the undertaking.
“Our elected officers ought to cease taking cues from the soiled fossil gasoline foyer and as an alternative take heed to Michigan residents, together with our 12 federally acknowledged Tribal nations, who’re urging President Joe Biden to revoke the presidential allow for Enbridge’s Line 5,” he mentioned. “Something wanting a shutdown is a grave risk to the environment, tourism, fishing, delivery, and Nice Lakes lifestyle.”
Nevertheless, Ryan Duffy, a spokesperson for Enbridge, informed the Michigan Advance that the protection of the Nice Lakes is strictly why the corporate stays dedicated to getting the undertaking throughout the end line.
“Enbridge is targeted on shifting Line 5 out of the water and into the Nice Lakes Tunnel as a result of defending the Nice Lakes is our high precedence,” he mentioned. “Our staff continues to make progress on plans for getting this achieved as quickly as doable. We’re additionally working to be aware of allowing companies as they full their opinions. The vast majority of folks in Michigan agree that the tunnel is one of the best answer for Line 5 going ahead.”
In the meantime, Nessel on Wednesday filed a short in federal court docket in help of the Unhealthy River Band of the Lake Superior Tribe of Chippewa Indians of the Unhealthy River Reservation of their lawsuit in opposition to Enbridge.
Enbridge’s Line 5 transports about 23 million gallons of crude oil and liquid pure fuel each day alongside a 645 mile stretch from Northwest Wisconsin into Michigan’s Higher Peninsula, below the Straits of Mackinac, by way of the Decrease Peninsula after which into Sarnia, Canada.
Earlier than it reaches the Straits, it strikes by way of a bit of pipeline on the Unhealthy River Reservation.
The tribe has argued that Enbridge is trespassing on their land, which a federal choose in Wisconsin agreed to in June, ruling that Enbridge should both shut down or reroute its Line 5 pipeline inside three years and pay greater than $5 million in income to the Chippewa Indians Unhealthy River Band.
Each Enbridge and the tribe subsequently appealed that call to the U.S. Court docket of Appeals for the seventh Circuit, and Nessel’s submitting was in help of the tribe’s enchantment.

“The proof on this case clearly establishes that Enbridge trespassed on the Band’s land and has operated Line 5 illegally since 2013,” mentioned Nessel. “This unlawful trespass creates a grave danger of an oil spill that will contaminate the Unhealthy River, the Reservation, and Lake Superior. On behalf of the Folks of the State of Michigan I’m taking this motion to guard our Nice Lakes from the risk posed by polluters who worth their very own backside line greater than our priceless pure assets.”
Nessel mentioned that erosion of the Unhealthy River’s financial institution threatens to reveal the pipeline on to the river, which “would virtually definitely trigger the pipeline to rupture and launch oil into the river, which flows instantly into Lake Superior.”
Wednesday’s submitting is simply the newest authorized salvo by Nessel in opposition to the pipeline. She first filed go well with in opposition to Enbridge in state court docket in June 2019 to decommission your complete pipeline. Nevertheless, the corporate gained a significant determination in August 2022, when a choose dominated that the case could be determined in federal court docket. Nessel then filed with the U.S. Court docket of Appeals for the Sixth Circuit to resolve the venue. That call remains to be forthcoming.